Raw Material Control: From Scrap to the Factory Material Certificate

Quality & inspection

Raw Material Control: From Scrap to the Factory Material Certificate

The factory material certificate verifies chemistry, mechanical and NDT results per heat, and it is written to the EN 10204 Type 3 structure. Learn how scrap control feeds the certificate and heat.

Published: · Last updated: · Reviewed by Wang Jingchun

An EN 10204 3.1 material certificate is issued by the manufacturer and states the actual chemical analysis, mechanical properties and NDT results for a specific heat — not a generic type. At SIMIS raw material control starts with the scrap charge and ladle analysis, is locked by the heat number, and ends with a 3.1 material certificate per heat that links every casting serial number back to that pour.

From Scrap Charge to Certified Material

Raw material control begins before the furnace. SIMIS segregates and verifies the scrap charge and alloy additions so the melt starts from a known base. From tap to certificate, the chain is: charge → EBT melt → LF refining → ladle analysis → pour with heat number → heat treatment → test coupons → the factory material certificate. Every step is recorded so the certificate at the end describes the real material, not an average.

Certificate Types and What 3.1 Contains

EN 10204 defines four certificate types. A 2.2 is a test report based on non-specific testing; a 3.1 is issued by the manufacturer's representative independent of production and declares the actual results of the specific heat. For railway castings the 3.1 is the working document: it carries the heat analysis, tensile and Charpy results at the specified temperature, and the NDT summary. A 3.2 adds an independent inspectorate witness. The 3.1 is what most AAR and GOST purchase orders require.

CertificateIssued byBasisUse
2.1ManufacturerStatement of complianceNon-critical
2.2ManufacturerTest report, non-specificGeneral
3.1ManufacturerActual results per heatRailway, pressure
3.2Manufacturer + independentWitnessed resultsHighest assurance

Melting, Analysis and Production Control

SIMIS charges from controlled scrap and alloy additions, then refines in an EBT electric arc furnace followed by LF ladle refining to hold sulphur low and chemistry tight. A spectrometer confirms the ladle analysis before pour, and the heat number is assigned at tap. This disciplined charge-to-tap chain is what makes the 3.1 certificate trustworthy: the numbers on the certificate are the numbers from that heat, not a grade average.

Traceability from Heat Number to Casting

Every casting is stamped or tagged with the heat number and a unique serial number. The 3.1 The material certificate lists that heat number and the mechanical and NDT results tied to it, so a buyer can match any casting in the field to its test data. SIMIS retains the melt records, coupon results and NDT films for the period stated in the contract.

Frequently Asked Questions

What is the difference between 2.2 and 3.1 certificates?

A 2.2 is a manufacturer's test report based on non-specific or representative testing and does not carry the actual values of your heat. A 3.1 is issued by an independent manufacturer representative and declares the real chemical, mechanical and NDT results of the specific heat, which is why railway purchase orders require 3.1 for traceable castings.

How is the heat number linked to the casting?

The heat number is assigned at tap and stamped or tagged on every casting from that pour, alongside a unique serial number. The factory material certificate lists that heat number with its analysis and test results, so any casting can be matched to its mechanical and NDT data and to the retained melt records.

Can the certificate be issued per casting or per heat?

The certificate is issued per heat, covering all castings poured from that heat, with the heat number linking each serial-numbered casting to the reported results. For first-article or critical lots a per-casting summary can be provided within the heat certificate. SIMIS confirms the certificate scope in the quotation and the material certificate.

Request a Quotation

Send your drawing and the required certificate type to sales@simisrail.com. SIMIS confirms receipt within 1 working day and returns a quotation with indicative lead time and MOQ, stating the EN 10204 certificate scope and heat-number traceability.

Technical Review

Where a grade is a substitute rather than an equivalent, that difference is stated on the page. For a question on the EN 10204 3.1 certificate, contact Felix at sales@simisrail.com or +86-13934165890.